Friday, 30 September 2011

East Norfolk Sixth Form College - Elliott OSBS Starting on Site

Picture_012

Elliott Off-Site Building Solutions has started on site for the development of the new canteen and two-storey classroom block at East Norfolk Sixth Form College.

The site set up works have been completed and the site clearance works are well underway to prepare the ground ready for the groundworks and foundations to begin.

The Elliott Off-Site team are due to complete the project by April 2012 and once completed, the whole south facing vista of the College site will include the five buildings constructed by Elliott Off-Site. The project will mark the third contract completed at the College by Elliott OSBS and continues a hugely successful relationship.

 

Friday, 23 September 2011

Carshalton High School – Final Blog

Carshalton-finalweek1
Carshalton-finalweek2

The new two-storey classroom block at Carshalton High School for Girls is now complete with all external works finished. The internal works have been completed to the client’s specification requirements and fixed and loose furniture have been added to all classroom and ancillary areas.

 

The project has been completed in time for the new term and pupils will be using the facilities with immediate effect.

 

This project continues the success of Elliott Off-Site Building Solutions in the Education sector over the last 50 years.

Friday, 16 September 2011

Carshalton High School - Week 14

Carshalton-week14

External works have been undertaken over the past week and have included a mixture of tarmac and paving flag pathways connecting the new building to the existing school buildings.

 

Internally the building is completed and is ready for the delivery of furniture and other school equipment. Once complete, Elliott Off-Site will undertake the making good of the site access route to return it to its original state.